Textile Unit

1

Damaged structure under repair

2

Patch up to the concrete section in progress

3

Fibre wrapping to the beam and column in progress

4

Work in progress during plant operation

Make OR Break Factor

All critical work had to be completed within 20 days of shut down.

THE CHALLENGE :

  • The entire structure of the textile unit was damaged by an extensive fire that had been triggered by a short circuit, thanks to faulty wiring.

THE ODDS :

  • All partial repairs had to be carried out in full operating conditions.

OUR RESPONSE :

  • A retrofit method was designed once the damage was evaluated
  • Grouting was done to the damaged core sections of concrete while patch repair was done to damaged concrete sections
  • Lastly, we reinforced some of the structural members with fibre-wrapping system